Friday, April 26, 2024
No menu items!
HomeFeaturesIs COVID-19 Effecting the Big Bar Landslide Work?

Is COVID-19 Effecting the Big Bar Landslide Work?

One thing the COVID-19 outbreak has not significantly affected is the work on the Big Bar landslide on the Fraser River. The Department of Fisheries and Oceans (DFO) said in a news release today that prime contractor Peter Kiewit Sons ULC is taking additional health and safety precautions, including tightening site access to limit the risk to workers.

DFO also says the landslide response continues to be a top priority, with resources remaining dedicated to the work. “Water levels remain low, and with the addition of a swift water rescue night-shift, crews are tackling crucial in-river work around the clock,” said the release. “This week, crews removed additional rock from the river, installed supports for the West Bank canopy, and improved the access route in multiple locations.”

Work continues throughout the night with crews excavating and armoring along the river. (photos courtesy of DFO)

In June 2019, huge pieces of rock caved off a 125-meter cliff, landed in the river, and created a five-metre high waterfall that returning salmon couldn’t navigate.

DFO says Kiewit is preparing for what is called the second East Toe blast. Crews have detonated charges to create a plateau on the rock outcropping to use as a drilling platform. They will move an air track drill to this shelf by heavy lift helicopter in the coming days. Drilling will then commence, with a blast scheduled in April.

Since mid-January, Kiewit has made steady progress at the site in the face of challenging weather and difficult access, according to the release. Despite Kiewit being successful in removing large boulders and debris, recent modeling done at low water shows that a mass of slide debris situated elsewhere in the river will cause heavy flows at high water, stopping fish passage.

The release says a team of internal and external experts has been developing contingency plans and designing alternative fish passage systems to move fish during high water, when passage will not be possible for an extended period of time. The plans include constructing a “nature-like” fishway, installing a pneumatic fish lift system, and developing a trap and transport option to collect salmon below the slide and release them upriver.

Contingency planning for the enhancement of stocks returning to the upper Fraser watershed is also ongoing, the release says. A monitoring program will be implemented throughout the salmon migration period to gather as much information as possible and to aid the implementation of the contingency plans.

DFO project staff met with Chief Roy Fletcher and Coordinator Dennis Fletcher from the High Bar First Nation (HBFN) March 9, and with Chief Patrick Harry and Coordinator Catlin Duncan from the Stswecem’c Xgat’tem First Nation (SXFN) on March 11 to review the proposed contingency plans. DFO also discussed options and plans with representatives of the Upper Fraser Fisheries Conservation Alliance. The release says no concerns regarding the proposed methodologies were raised during the discussions.

The participants requested regular updates on next steps and their continued involvement as all three levels of government work to reduce the slide’s impact on 2020 salmon returns and beyond.

The response to the Big Bar landslide is collaborative, said the release, and teams will continue to work with communities to ensure they remain an integral part of the planning, operations, and decision-making process. Sustained efforts will be required in the short- and long-term, possibly into years ahead, to reduce the impact of the landslide on future salmon stocks, said the release.

For more information, you can visit DFO’s Big Bar Landslide Response webpage or the Province of BC’s Big Bar Landslide Incident webpage.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.